The radar installation was started on 7 February 2009
Future radar picture

Site visit by Timbalan Ketua Pengarah Keselamatan Malaysia Yang Berbahagia En.
April 2009 progress
May 2009 progress - radar platform base ( stage 1 with concrete grade 35)
Jun 2009 progress
July 2009
August 2009 -
End of August, main road to radar site progress
September 2009 - Signage Location
- Site Acceptance test (M&E, C&S)
October 2009 - Radar Site with temporary fencing
November 2009 - Furniture for equipment room installed

-radar head container arrive on 24 November 2009

Disember 2009 - New water meter installed

January 2010 - Anti climb fencing installation in progress

February 2010 - Technician setting up the radar room