The Supply of Primary & Secondary Radar Systems and Upgrading of Malaysia Air Traffic Services Modernization Programme at Tawau, Sabah : update

March 2010 : radar head has been installed


Mr. Haizar Farewell Party

Haizar@Bamba farewell party was held at Hotel Emas on the 20.03.2010. We wish you good luck on your career wherever you go




Wednesday, March 17, 2010

Validation Check For New Intake


Validation Check started yesterday and today for Mr. Husro and Mr. Fadzli, we wish both of you good luck and all the best..

Monday, March 15, 2010

Bringing Back The Memories

Tawau Old Airport

Taken from www.discovertawau.com

Dialogue with PW2

Dialogue with PW2, Tuan Mahmud Amat Shah and Timb. Pengarah ATCC Kinabalu, Mr. Wong Sie Tzen on the March 11, 2010
Radar site visit before the dialogue

Eagle Sucked into plane's engine

Eagle Sucked into plane's engine

Taken from Daily Express December 10. 2004

Thursday, March 4, 2010

DCA TAWAU FC NEW JERSEY


After a few month selling soft drinks+ collection, finally we(DCA TAWAU FC) manage to buy our own jersey/ball. Above pic from left: Pejoe(captain), Win, George(Manager). Below pic: some of the DCA TAWAU FC members.

Hopefully with this new jersey, everybody will be more active.

Finally 'Majulah Sukan Untuk DCA'







PANS-OPS MEETING


PANS-OPS meeting was held at Tawau DCA on the 23 February 2010.
Front from left : Muddatstsir Bin Mashor, Azli @ Azmin Bin Faizol, Sio Yew Hua, Tn Hj Abdul Razak Bin Ali, George Ng.
Behind from left: Haizar Abd Halim, Mohd Azizi Che Soh, Mohd Isa Amatshah, Loh Yew Khang

Tuesday, March 2, 2010

The Supply of Primary & Secondary Radar Systems and Upgrading of Malaysia Air Traffic Services Modernization Programme at Tawau, Sabah, Malaysia


The radar installation was started on 7 February 2009








Future radar picture






Site visit by Timbalan Ketua Pengarah Keselamatan Malaysia Yang Berbahagia En. Nik Azlan Bin Abas on the 23 March 2009










April 2009 progress









May 2009 progress - radar platform base ( stage 1 with concrete grade 35) and site visit by TPW2 Mr. Sio Yew Hua on the 21 May 2009








Jun 2009 progress








July 2009








August 2009 - Fibre Optic & Electric Cable Path way installation

























End of August, main road to radar site progress









September 2009 - Signage Location








- Site Acceptance test (M&E, C&S)









October 2009 - Radar Site with temporary fencing







November 2009 - Furniture for equipment room installed










-radar head container arrive on 24 November 2009









Disember 2009 - New water meter installed










January 2010 - Anti climb fencing installation in progress










February 2010 - Technician setting up the radar room